3                                            Project Description

3.1                                      Project Scope

The location and alignment of the Project components are shown in Figure 3.1 to 3.5.  The scope of the Project comprises:

·         Improvement of an approximately 4.5km long section of Shenzhen River;

·         Re-provision of a boundary patrol road and about 4.5km of boundary fence;

·         Dry weather flow interception along Shenzhen side of the river; and

·         Associated landscaping works.

3.2                                      Project Design

3.2.1                                River Modification Works

The proposed river modification works under the Project are summarized in Table 3.1.  The work areas of the Project are shown in Figure 3.6. 

Table 3.1        River Improvement Works

Works Area

Section

Chainage

Length (m)

Works Descriptions

I

Liantang BCP

16+458 to 17+930

1,472

River widening; embankment works; boundary patrol road and boundary fence construction; sewage diversion

II

Heung Yuen Wai BCP

15+458 to 16+458

1,000

River widening; embankment works; boundary patrol road and boundary fence construction; sewage diversion

III

Luo Fang Bridge to Flood Retardation Pond

14+463 to 15+458

995

River widening; embankment works; boundary patrol road and boundary fence construction; sewage diversion; flood retardation pond construction.

IV

Luo Fang Bridge and downstream

13+465 to 14+463

998

River widening; embankment works; boundary patrol road and boundary fence construction; sewage diversion; Luo Fang Bridge and Police Kiosk reconstruction.

Under the proposed Stage 4 regulation, about 4.5km section of the Shenzhen River will be regulated.  The work starts from the confluence with Ping Yuen River (ie the endpoint of Stage 3 regulation works) and will pass through the Luo Fang Sewage Treatment Works, Luo Fang Bridge, Luo Fang Village, Sai Ling Village in Shenzhen and Kaw Liu Village and Chuk Yuen Village in Hong Kong, and ending near Pak Fu Shan in Hong Kong.

The design principle of the works is to protect the livelihood of residents on both sides of the river with an ecological sensible design, which should maintain the naturalness of the river and riparian habitats and hence protect the biodiversity.  As shown in Figures 3.1 to 3.5, the design alignment will follow the existing watercourse as far as possible to minimise alternation to the existing river profile and meandering nature, minimise landtake and avoid massive excavation and filling.  Moreover, the river bed will remain as natural bottom without concreting.  At several meandering locations with sharp bend, a floodplain will be created with the planting of existing species to resemble the naturalness of the river while achieving the required flood design standard.

Trapezoid channel design will be used in most of the river regulation works.  The bottom width will be in a range of 14 to 16m and will be increased to 30m when approaching the downstream outlet.  The top width of these river sections will be limited to 60m and the slope of sidewalls at Shenzhen side and Hong Kong side will be in range of 1:2 to 1:3 and 1:2.5 to 1:3, respectively.  The area at the top of embankment will be used as boundary patrol road and maintenance services berm. Typical trapezoid channel is shown in Figure 3.7.

Compound channel design will be used to suit actual site conditions.  The design will be harmonized with the existing natural environment with an aim to minimize the disturbance of ecological habitats.  Different features like flood channel and marshland areas will be incorporated into different sections of the river in order to resemble the existing river condition.  The height of the sidewall will be about 1 to 2m and the slope of the sidewall will be in the range of 1:3 to 1:5. Typical section of compound channel is shown in Figure 3.8.

Vertical sidewall should be adopted in area where further modification is limited by site constraint especially those in the Shenzhen side where land for trapezoidal channel is not available.  It is estimated that about 240m of the river will be regulated into vertical channel with 4 to 5 m high vertical sidewall.  The top width of the sidewall will be about 1m. Typical river section design with vertical sidewall is shown in Figure 3.9.

The proposed flood retardation pond will be located at chainage 14+778 to 15+183 on the Shenzhen side covering an area of 22,000 m2 with a storage capacity of 80,000 m3.  Overflow weir will be used at the inlet of the retardation pond.  Water will enter into the retardation pond when the water level at the inlet is higher than the weir.  Flood water will be discharged back to the river through control gates when the water level in the river is lower than that in the retardation pond.   Landscape treatment with design compatible with the surrounding area will be provided to the flood retardation pond, including the isolated islands in the pond.

3.2.2                                Reprovisioning of Boundary Patrol Road and Boundary Fence

The reprovisioning of boundary patrol road and boundary fences along the concerned section of Shenzhen River under the Stage 4 regulation has already been incorporated into the design and construction programme of this Project.

Hong Kong Side

The design of boundary patrol road in Hong Kong side will be based on the Transport Planning and Design Manual and Guidance Note published by the Highways Department of HKSAR.  The total length of the boundary patrol road to be reprovided under this Project is about 4.5km and the width will be 3.5m.  The boundary patrol road will be paved with asphaltic concrete.  Passing bays (12m long and 6m wide) will be provided at 200 to 300m intervals.  Boundary fences will be constructed on both sides of the boundary patrol road.  The height of secondary and primary boundary fences will be 3.5m and 4.6m respectively and the primary fence will be equipped with security sensing system and barbed wire.  The typical section drawing of boundary fences and boundary patrol road are shown in Figures 3.10 and 3.11. 

The reprovisioning of the section of boundary patrol road and boundary fence along the section of Shenzhen River under this Study will be managed by DSD as an “advanced works” of this Project.  Currently, the Architectural Services Department (ArchSD) is managing the construction of a secondary boundary fence and reprovision of boundary patrol road from Pak Hok Chau to Sha Tau Kok. 

Shenzhen Side

Dry weather flow interception will be carried out at the river bank of Shenzhen side.  The existing boundary patrol road and boundary fence affected by the construction of the new sewer will need to be demolished and reprovided.  In addition, a section of boundary patrol road and boundary fence will need to be reconstructed due to realignment of the Shenzhen river near the proposed LT/HYW BCP.  A total of about 2,630m of the boundary patrol road and boundary fence at the Shenzhen side (upstream of Luo Fang Bridge) will be reprovided.  The standard width of the new boundary patrol road and height of the new boundary fence on the Shenzhen side will be 6m and 3.5m, respectively.  The boundary patrol road will be paved with concrete.  Table 3.2 summarizes the details of the new boundary patrol road and boundary fence at the Shenzhen side.

Table 3.2        Reprovisioning of Patrol Road and Boundary Fence at the Shenzhen Side

Chainage

Length (m)

Reprovision Rationale

15+300 to 16+180 and

17+162 to 17+930

1,648

Sewer for dry weather flow interception works will be laid under the existing patrol road. Open trench method will be used and boundary fence will need to be removed during construction.

 

16+180 to 17+162

982

The river will be shifted to the east in order to accommodate the planned LT/HYW BCP.  The boundary patrol road and boundary fence will need to be reprovided in this section.

3.2.3                                Dry Weather Flow Interception at Shenzhen Side

Currently, the separation of sewage from stormwater in Shenzhen is not very effective and stormwater discharge points at Shenzhen side into the Shenzhen River is polluted.  As part of this Project, the dry weather flow from these outflows will be collected and diverted to the Luo Fang Sewage Treatment Works in Shenzhen in order to improve the water quality of Shenzhen River.     

24 overflow manholes will be constructed to collect the dry weather flow and gravity sewer will be built to convey the dry weather flow to the Luo Fang Sewage Treatment Works.  During the wet season, the rainwater overflow from the manholes will be discharged into Shenzhen River.  The design and construction of the dry weather flow interception can be divided into two sections which are summarized in Table 3.3 and shown in Figure 3.12.

Table 3.3        Dry Weather Flow Interception at the Shenzhen Side

Section

Chainage (Sewerage at Shenzhen Side)

Length (m)

Diameter (mm)

End Point Connection

Site Constraints

Project’s end point (upstream) to sewage tunnel

 

JW3+026 to JW1+435

1,591

1,000

Connect to existing sewage tunnel at JW1+435

Most of the sewer will be constructed underneath the new boundary patrol road

Sewage tunnel to Project’s start point (downstream)

 

JW1+435 to JW0+000 

1,435

1,200

Connect to Luo Fang Sewage Treatment Works at JW0+000

Sewer will be constructed underneath the existing or new boundary patrol road 

3.2.4                                Landscaping Works

The landscaping works along the river embankment, channel sides and flood retardation pond will be designed to re-establish the natural riparian ecosystem with the aims to enhance the local biodiversity, protecting the water resources and avoid erosion.  Vegetations chosen for the landscaping works will be based on the following criteria:

·         Well adaptive to the environment – mainly use native species supplemented by suitable exotic plants;

·         Able to enhance the local biodiversity – mixed vegetations of arbour, groundcovers and grasses will be placed along the river;

·         Low management requirements – those species with low management requirements will be chosen to minimize the maintenance cost; and 

·         Prevent obstruction of sight view - design should fulfil the security requirements for boundary patrolling and therefore should not obstruct the sight view along the boundary patrol road.   

The landscape characters along the river course will be designed with considerations of local characteristics and the landuse planning in the adjacent area. 

The preliminary proposed landscape treatment along the sloped river bank can be classified into three types: natural vegetation, semi-natural and artificial.  The main materials and functions of each type of treatment are shown in Table 3.4.

Table 3.4            Common Landscape Treatment

Type of Treatment

Protection Function

Ecological Function

Use of Material

Cost and Construction

Natural Vegetation

·                      less resistant to water flow;

·                      usually used at river sections with lower velocity (1-3m/s)

·                      can retain pollutants;

·                      high vegetation cover;

·                      can provide better habitats for organisms

·                      use natural soil and natural materials

·                      low cost; simple human maintenance

Semi-natural Vegetation

·                      can resist 4-6m/s water flow;

·                      better and more stable revetment in general

·                      can better retain pollutants;

·                      use the space between wood log and rock to carry out hydraulic and provide habitats for organisms;

·                      vegetation cover rate not high at the beginning

·                      natural or semi-natural materials;

·                      civil engineering materials being high polymer; stable chemical nature

·                      lower cost; simple human maintenance; easy construction

Artificial

·                      can resist strong water flow;

·                      some can resist velocity over 6m/s

·                      can retain pollutants;

·                      greening is possible at water with frequent changes

·                      materials include steel and cement elements;

·                      strong materials

·                      higher cost; higher standard required for construction

Detailed landscape design for the Project will be submitted to the relevant authority for approval during the detailed design stage.

3.3                                      Construction Programme

The construction phase of the main works will last for 44 months.  An advanced works contract on the construction of boundary fence and boundary patrol road on Hong Kong side will be included as part of this Project and will last for about 36 months between the period of February 2012 and January 2015.  The proposed construction programme is presented in Table 3.5 and shown in Figure 3.19.

Table 3.5        Construction Programme

 

Phase

Date

Duration

Works Description

1

Advanced Works

February 2012 to January 2015

36 months

Construction of boundary fence and boundary patrol road on HK side

2

Preparation Phase

March to July 2013

 

5 months

Tendering; land resumption

3

Pre-construction

August to September 2013

2 months

Construction of site access roads and site office, site clearance, site preparation works etc.

 

4

Construction

October 2013 to December 2016

39 months

Main construction works of the Project such as dredging of river sediment and soil excavation, construction of flood retardation pond, boundary fence and boundary patrol road on Shenzhen side, river modification works, dry weather flow interception works etc.

 

5

Post-construction

January 2017 to March 2017

3 months

Demolition of temporary structures, landscaping works etc.

3.4                                      Construction Methodology

Temporary river diversion will be carried out, if necessary, before the commencement of the construction of the regulation works.  The main construction works include boundary patrol road and boundary fence, temporary river diversion, soil excavation, embankment construction, sewage diversion works and landscaping works.

3.4.1                                Advanced Works - Reprovisioning of Boundary Patrol Road and Boundary Fences

The reprovisioning of boundary patrol road and boundary fences under this Project will be coordinated with ArchSD’s Construction of a Secondary Boundary Fence and New Sections of Primary Boundary Fence and Patrol Road contract.  The site will be cleared and excavated or filled to the designed road level with minor earth retaining work.  Reinforced concrete footing for the fence will be cast in-situ.  Steel fence will then be erected.  The patrol road will be paved with asphaltic concrete.

3.4.2                                River Diversion

Water will be diverted before the commencement of the soil excavation and construction works.  A longitudinal cofferdam will be built at the central of the designed river course to meet the design criterion for 5-year design period and will be kept as “diversion dyke”.  The cofferdam will be made of hessian bags with clay and the surface will be laid with impermeable membrane.  Additional cofferdams will be built across the river in 200 to 300m intervals of the designed river course to meet the need of construction.  A typical cross-section showing the river diversion work and the sequence of construction at the river is shown in Figure 3.13.

When the excavation and placement of embankment foundation are carried out on one side, the river course on the other side will be used as diversion channel.  

3.4.3                                Excavation Works

As shown in Figure 3.13, after the cofferdam is built and the inside of the cofferdam is dewatered, excavation will be carried out in dry condition within the cofferdam.  The river bank will be excavated by backhoes of 2 m3 capacity.  The original river bed will be excavated by backhoes of 1 m3 capacity or long boom backhoe of 0.55 m3 capacity.  Once the excavation of river bed is completed, the cofferdam will be demolished using the backhoes or long boom backhoe.

The excavated spoils will be transported by dump trucks and temporarily stored at the stockpiling area within the Project Site (see Figure 3.14 to Figure 3.17).  It is estimated that about 690,200 m3 of excavated materials will be generated, of which about 95,000 m3 of excavated soil will be reused on-site.  The contaminated river sediments (about 70,000 m3) will be disposed of at the Contaminated Mud Pit at East Sha Chau (Hong Kong) or other designated mud pit authorised by the CEDD while the surplus excavated soil and category L sediment will be transferred to Huangmao Dao (黃茅島) managed by Shenzhen.  Both contaminated river sediments and surplus excavated soil will be transferred off-site by truck to Shekou Pier and then loaded to barges for re-exporting to designated disposal areas.  Subject to the sediment testing results, the quantities of contaminated river sediments may be refined in later stage.

3.4.4                                Embankment Construction

New dykes on both sides of the river course will be constructed with the excavated soil from the excavation works.  Wheel loaders with capacity of 2 to 3 m3 will be used for earth moving.  10-tonnes self-unloading trucks, 74-kw bulldozers and 10-tonness vibrating rollers will be used for materials transportation, paving and compacting respectively.  After excavation of the foundation has been completed, placement of filling materials will be carried out and the thickness of each filling layer will be between 300 to 500 mm.

3.4.5                                Slope Protection Works and Construction of Retaining Walls

Geotextile and crushed rocks will be laid on the slope surface of the river bank after excavation and modification works.  No-fines concrete and concrete block will be placed on the surface.  The retaining walls along the river banks will be constructed by gabion wall or concrete wall.       

3.4.6                                Dry Weather Flow Interception Works at Shenzhen Side

The sewers will be laid by open trench method.  Trench support measures will be used for excavation deeper than 1.2m below existing ground level.  All open trenches will be covered as soon as practical after placement of the sewers.  

3.4.7                                Landscaping Works

Landscaping works will be carried out after the completion of embankment construction and slope protection works.  The works will be carried out at suitable seasons under the supervision of qualified landscape professionals ([1]). 

3.5                                      Maintenance Dredging

It is revealed in the sediment modelling result that the amount of sedimentation in the section of Shenzhen River within the Project Site is minimal, due to the fact that the gradient of the concerned river section is relatively steep and the river is not affected by tidal movement.  Hence, only small scale maintenance dredging activity along the river channel is anticipated at regular intervals (the frequency will be determined through sediment monitoring in the operation stage), and the scale of maintenance dredging will be very small as compared with the dredging works during the capital works construction.  Maintenance dredging will mainly be conducted in dry season.

Maintenance dredging of sediment may be required at the flood retardation pond on Shenzhen side and will be carried out by the Shenzhen side.  The flood retardation pond will only be used for water storage during severe rainstorm event in the wet season, and therefore the rate of sediment accumulation in the pond is expected to be small.  As such, and given that the size of the pond is only about 2.2 ha on plan, the scale and volume of the maintenance dredging, if required, is anticipated to be significantly smaller than that during the capital works construction.  It is worth to note that the flood retardation pond is a confined area, any suspended river sediments associated with dredging will eventually settle within the pond without causing any sediment release into the river.

3.6                                      Concurrent Projects

It is noted that the following projects will be carried out concurrently in the vicinity of the Project Site:

·         LT/HYW BCP and the associated works;

·         Construction of a Secondary Boundary Fence and New Sections of Primary Boundary Fence and Patrol Road; and

·         Drainage Improvement in Northern New Territories, Package C (Remaining Works).

There are two planning studies with study areas within and in the vicinity of the Project Site:

·         Land Use Planning for the Closed Area; and

·         New Development Areas in North East New Territories.

The locations of the concurrent projects and the planning study areas are shown in Figure 3.18.

LT/HYW BCP and the Associated Works

By connecting with the Eastern Corridor in Shenzhen, the proposed LT/HYW BCP will provide an efficient access to the eastern part of Guangdong Province.  The proposed new BCP will satisfy the long-term transport needs and help re-distribute the cross-boundary traffic amongst the crossings in the eastern part of the territory and will alleviate the frequent traffic congestion at the Man Kam To and Sha Tau Kok BCPs.  The scope of work of this Project also includes the relocation of Lin Ma Hang Road and resite of Chuk Yuen Village.

It is anticipated that the construction of the LT/HYW BCP and connecting roads will commence at the end of 2013 and be completed in end 2018.  The planned construction period for the resite of Chuk Yuen Village is from late 2010 to early 2012 for population intake by early 2013.

Construction of a Secondary Boundary Fence and New Sections of Primary Boundary Fence and Patrol Road

This project mainly comprises the construction of a secondary boundary fence (SBF) along the southern edge of the existing boundary patrol road (BPR) (approximately 21.7km) from west (Pak Hok Chau) to east (Sha Tau Kok).  For sections where the existing primary boundary fence (PBF) runs along the southern edge of the BPR, a new fence with sensor alarm system will be constructed on the northern edge of the BPR as part of the PBF whereas the existing PBF will be modified to become the SBF.  The project also includes the conversion of the existing maintenance services road along the Shenzhen River bank to the north of the Lok Ma Chau Loop and Hoo Hok Wai into a new section of the BPR with a PBF and a SBF; and construction of two new sections of the BPR with a PBF and a SBF along the Shenzhen River side to the north of Pak Fu Shan and northwest of Lin Ma Hang Village.  In addition, the Project includes the construction of a checkpoint at the entrance to the Sha Tau Kok town and replacement of the existing checkpoint at Pak Hok Chau, removal of the existing checkpoints at Lok Ma Chau, Sha Ling, Ping Che and Shek Chung Au, and removal of the existing PBF along those sections of the existing BPR which will be replaced by new sections of the BPR.

Based on the advice from ArchSD, the latest tentative construction programme shall be from end 2011 to early 2013 (section from Ng Tung River to Ping Yuen River) and from end 2011 to end 2013 (section from Pak Fu Shan to Lin Ma Hang Road).

Drainage Improvement in Northern New Territories, Package C (Remaining Works)

The Project comprises the improvement of Ping Yuen River through construction of 1.9 km of Drainage Channel TKL05 in Ta Kwu Ling.  The construction works will mainly involve site clearance, site preparation, earthworks and other general construction activities.  The operation phase works will primarily be the routine maintenance and operation of the completed drainage channel.  The construction work is scheduled to commence in late 2012 and completed by 2016.

Land Use Planning for the Closed Area

To formulate the land use framework to guide future preparation of statutory town plans for the area to be released from the Closed Area before the completion of the secondary boundary fence, Planning Department has embarked on a planning study Land Use Planning for the Closed Area (hereafter “the Closed Area Study”), to carefully examine the development potential and constraints of these areas.

The Closed Area Study was completed in July 2010 and the planned land uses along the Project Area include the “Village Type Development” (“V”), “Recreation” (“REC”) and “Green Belt” (“GB”).  Nevertheless, the schedules and programs of those FCA Study proposals (particularly “V” and “REC”) should be subject to private initiatives and market-driven factors while the development schedule and programme of the NENT NDAs Study are still not available at this stage.  Based on the Recommended Development Plan of the Closed Area Study, it is not anticipated that there will be large-scale developments in the vicinity of the Project in addition to the development of the LT/HYW BCP.

New Development Areas in North East New Territories

The North East New Territories New Development Areas Planning and Engineering Study (hereafter “the NENT NDAs Study”) formulates the development plans for the NDAs in Kwu Tung North, Fanling North and Ping Che / Ta Kwu Ling (PC/TKL).  The nearest NDA to the Project Site is PC/TKL NDA, which is located at more than 600m from Shenzhen River.  According to the Preliminary Outline Development Plan of the NENT NDAs Study, PC/TKL NDA is planned for accommodating high value-added non-polluting special industries, the six industries (including testing and certification services, innovation and technology, cultural and creative industries, environmental industries etc), port back-up and logistics industries and low to medium density residential developments.  The NENT NDAs Study is in progress and there is no confirmed development schedule and programme yet.  As advised by the project proponent of the NENT NDAs Study, the earliest construction works in PC/TKL NDA is unlikely to commence before 2017.  As such, it is anticipated that no works in PC/TKL NDA would be conducted concurrently with the works under this Project. 

3.6.1               Cumulative Environmental Impact

As the above two concurrent projects (LT/HYW BCP and the Associated Works and Construction of a Secondary Boundary Fence and New Sections of Primary Boundary Fence and Patrol Road) will have construction works undertaken concurrently in close proximity to Project Site, there is a potential for cumulative construction phase impacts, including dust, noise, water quality, waste, ecology and landscape and visual, which need to be assessed in this EIA. 

Of particular to note, the reprovisioning of boundary patrol road and boundary fences along the concerned section of Shenzhen River under the Stage 4 regulation has already been incorporated into the design and construction programme of this Project.

The Drainage Improvement in Northern New Territories, Package C (Remaining Works) project is subject to another future detailed EIA Study and detailed construction programme is not available at this stage.  The cumulative impact cannot be assessed at this stage.  However, since the drainage improvement works is located at about 500m from the Site and given its nature and scale of works, adverse cumulative impact is not anticipated.

The schedules and programs of those FCA Study proposals should be subject to private initiatives and market-driven factors.  Hence, it is not possible to assess the cumulative impact at this stage. 


 



([1])   A professional member of relevant landscape institute.